PPAP deliverable guide
How to complete Control Plan
The Control Plan translates product requirements and PFMEA controls into work that can be executed and recorded in production.
Complete the fields
- Header and revision control
- Record part number, part name, customer, plant, process type or phase, Control Plan number, revision, date, preparer, and approval status required by your format.
- Process step
- Use the same process-flow step number and name.
- Characteristic and specification
- State the product characteristic or process parameter, its requirement, target, tolerance, or specification source.
- Method and measurement system
- Identify the measurement or monitoring method, gauge, fixture, test equipment, software, or verification approach.
- Sample, frequency, and responsibility
- State what is checked, how many or how often, and the responsible role. Avoid “as required” unless the referenced instruction defines it.
- Record and reaction plan
- Identify the record and write the specific containment, segregation, notification, correction, and release/restart steps when a result is unacceptable.
Step-by-step completion sequence
- Start with customer requirements, process flow, PFMEA controls, and approved special-characteristic classifications.
- Build one row for each required control at the applicable process step.
- Verify every method, frequency, record, and reaction can be performed at the point of use.
- Review with production, quality, maintenance, and material-handling roles.
- Approve, train to, audit, and update the plan when risks or processes change.
PPAP control point: The customer’s current submission request, customer-specific requirements, and approved forms control. This guide explains a practical way to prepare the record; it does not authorize a substitute format or acceptance criterion.